Metop-B Commissioning

METOP-B in Commissioning

Following a successful handover to EUMETSAT from ESA/ESOC, on 20 September, Metop-B is now in commissioning.

 

The timeline below gives details of the commissioning activities.

Last Updated: Thursday, 24 January, 2013 8:42

Timeline

Key milestones for the post-launch commissioning phase, including details on when instruments are switched on and tested, and when data starts to become available for users

Commissioning milestones
Title Activity Date/Status
Handover Handover of Metop-B to EUMETSAT Completed
20 September
SIOV Start Satellite In-Orbit Verification (SIOV) begins Started
Final orbit phasing achieved Completed
Payload verification Solid State Recorder Completed
HRPT switch on
HRPT verification
Completed
Completed
Search & Rescue on Completed
ADCS Receiver and Transmitter on Completed
AVHRR & HIRS doors opening Completed
IASI mechanisms release Completed
GOME Coolers Fully Activated Completed
IASI, HIRS & AVHRR outgassing Completed
IASI First Data (Without on-board processing) Completed
IASI First Data (With on-board processing) Completed
GOME Sun Calibrations Started Completed
SARR/SARP Active (SARR A-side) Completed
Direct Readout Available Service continuously available according to the schedule below  
AVHRR visible channel Available
GOME Available
First MMAM Available
AMSU A1& A2 Available
ASCAT Available
MHS Available
GRAS Available
ADCS Available
SEM Available
HIRS/4 Available
AVHRR/3 IR Available
IASI Available
SIOV ends End of Satellite In-Orbit Verification (SIOV) phase Completed
Global Data to Cal/Val Partners AMSU-A1, A2 Available
AVHRR/3 VIS Available
GRAS Available
MHS Available
HIRS/4 Available
ASCAT Available
AVHRR/3 IR Available
GOME-2 Available
IASI Available
Global Data to all users Pre-operational data progressively made available per product processing facility L+ 2–7 months
AMSU-A1, A2 Available
AVHRR/3 Available
GRAS Available
MHS Available
HIRS/4 Available
ASCAT Available
GOME-2
IASI
Regional Data to all users EARS-AVHRR L+ 19 weeks
EARS-ATOVS L+ 19 weeks
EARS-ASCAT L+ 23 weeks
EARS-IASI L+ 25 weeks
Satellite Operational Metop-B becomes prime satellite L+ 7.5 Months